Project Updates
OCTOBER 2007
Completed Projects:
- Banyan Ridge
- Mandala West
- Mandala North
- Mandala South
Upcoming Project:
Mandala 2
Activity: Road Tracing

Ongoing Projects:
- The Ranch
-Gate and Guard House -Land Development
- Mandala East
-Land Development
- Spine Road
-Phase 2A - 1st 2 Lane -Concreting of 3rd Lane
------ The Ranch Gate and Guardhouse ------
Accomplishment 95.68%

The Ranch Land Development

Accomplishment 97% (As of October 8, 2007)
| Drainage System |
90% |
| Water System |
98% |
| Road Concreting |
100% |
| Sodding Works |
70% |
*Sodding and Block Preparation

*Rectification Works

------ CONSTRUCTION OF HOUSE MODELS AT THE RANCH ------
| HOUSE MODEL |
ACCOMPLISHMENT |
| Upland |
71% |
| Ridge Deck |
69.46% |
| Hartford |
77% |
UPLAND HOUSE MODEL (Blk 3 Lot 6)
*CHB Laying

*Installation of roof framing for Upland

RIDGEDECK HOUSE MODEL (Blk3 Lot 3)
*CHB Laying

*Construction of entrance stairs of Ridgedeck

*Construction of CHB wall partitions at 2nd floor of Ridgedeck

HARTFORD HOUSE MODEL (Blk1 Lot 5)
*Wall plastering and installation of concrete mouldings

*Stairs at Hartford
 
----- Mandala East Land Development -----
Accomplishment 97% (As of October 8, 2007)
| Drainage System |
100% |
| Water System |
81.29% |
| Road Construction |
100% |
| Masonry Barrier |
100% |
Road 17: Concreted
.png)
Road 14 Concreting

----- Spine Road -----
Accomplishment (As of October 8, 2007)
- PHASE 2A 97.54%
Drainage System 92.37% Road Works 100%
- 3RD LANE 73%
Road Works 82%
1st & 2nd Stage Road Concreting at The Ranch Entrance
 
1st Stage Road Concreting at Mandala Phase 2 Entrance

Base Course Preparation and Formworks for Curb & Gutter: Center Island